Moldova opens a new power line to Europe and says it buys zero Russian gas
On November 8, Moldova opened the 400 kV Vulcanesti-Chisinau line, which bypasses the Cuciurgan power plant and links the country to Europe's grid.
الحدث: 8 نوفمبر 2026
المصدر الأساسي: 8 نوفمبر 2026
نُشر هنا: 8 نوفمبر 2026 في 08:57 م UTC
اقرأ: 2 دقيقة
ماذا حدث
On November 8, Moldova opened the Vulcanesti-Chisinau power line, a 400 kV line of about 157 km. It bypasses the Cuciurgan power plant on the left bank of the Dniester and adds a new route to import power from Romania. The project cost about 61 million euros, backed by the World Bank. President Maia Sandu wrote that Moldova buys zero Russian gas.
لماذا يهمك
The line can carry up to 630 MVA, more than half of the country's peak demand. So Moldova relies less on one plant and can buy power where it is cheaper. For the region it is a step toward the EU's shared power market. This is our view.
ماذا تتحقق منه وتراقبه
Watch Moldova's power prices this winter and the two next lines to Romania: Balti-Suceava and Straseni-Gutinas. This is an overview, not advice.
أين يحدث ذلك
LIVEاسحب للتدوير. النقاط الخضراء: البورصة تتداول الآن (الساعات العادية، دون احتساب العطل). الظل: حيث الليل الآن. الحدود: Natural Earth، الزلازل: USGS. فكرة الطبقات: God’s Eye View (MIT).
What happened. On November 8, Moldova opened the Vulcanesti-Chisinau line. It is a 400 kV overhead line of about 157 km that links the Vulcanesti substation in the south with the Chisinau substation. It bypasses the Cuciurgan power hub, which Energy Minister Dorin Junghietu says is controlled by the authorities in Tiraspol. President Maia Sandu and EU Enlargement Commissioner Marta Kos attended the launch.
How much it adds. Moldova 1 reports the line can carry up to 630 MVA, more than 50% of Moldova's consumption at peak times. Power comes from Romania and, more widely, from the European grid of ENTSO-E operators. The whole project cost about 61 million euros, with about 27 million euros for the line itself. The World Bank approved the financing in 2019.
Why it took so long. The line was first meant to start in August 2024. Building ended in November 2025, followed by testing and substation upgrades. Moldova 1 had earlier reported a delayed transformer.
What comes next. Sandu wrote on X that Moldova buys zero Russian gas and that two more lines to Romania are on the way. The first, Balti-Suceava, costs about 77 million euros, including a 15.4 million euro EU grant plus EBRD and EIB funds, with building from 2027. The second, Straseni-Gutinas, has 130 million dollars from the US and is due by 2032. Marta Kos said Moldova's dependence on Russian energy has ended.
حقائق مؤكدة
- On November 8, 2026, Moldova opened the 400 kV Vulcanesti-Chisinau power line, about 157 km long.[2][3]
- The line bypasses the Cuciurgan power hub and adds a route to import power from Romania and the ENTSO-E grid.[2]
- It can carry up to 630 MVA, more than 50% of the country's peak consumption.[2]
- The project cost about 61 million euros, with World Bank financing approved in 2019.[2][3]
- Maia Sandu wrote that Moldova buys zero Russian gas and that two more power lines to Romania are on the way.[1]
- The Balti-Suceava line costs about 77 million euros with building from 2027; the US approved 130 million dollars for Straseni-Gutinas, due by 2032.[2]
التبعات
- مؤكدMoldova now has a second major route to import electricity from Romania.
- قراءتناIt will be easier for the country to buy power on the European market and harder for one plant to cut its lights. This is our view.
- قراءتناPower bills will not drop right away: prices depend on the market in Romania and the EU. This is our view.
لا يزال مجهولًا
- How household power tariffs will change
- How much power Moldova will actually import over the new line this winter
- Whether the next two lines will be on time
من يتأثر
Moldova, Romania, Europe. People in Moldova and Romania, and anyone tracking European energy and power markets
المصادر
- Maia Sandu, President of Moldova (X): Today we launched the Vulcanesti-Chisinau power line 8 نوفمبر 2026 · رسمي
- Moldova 1 (TRM): Moldova inaugurates strategic Vulcanesti-Chisinau power line 8 نوفمبر 2026 · إعلام
- Logos Press: The Vulcanesti-Chisinau power line has been inaugurated 8 نوفمبر 2026 · إعلام
الغلاف: رسم Freekonomist، صورة رمزية، لا صورة للحدث. هذا شرح إخباري، لا نصيحة مالية.
المزيد من القصص
BBAS3: Banco do Brasil stock drops over 10% as Q3 profit falls 66.5%
BBAS3, the Banco do Brasil share, fell more than 10% in early trade on 12 November after third-quarter profit dropped 66.5% to R$1.27 billion, farm-loan defaults rose and the bank cut its guidance and payout.
India inflation hits 6.09%, a two-year high above the RBI band
India's retail inflation rose to 6.09% in October from 5.54% in September, breaking above the central bank's 2-6% tolerance band. Food is the main driver, up 8.94%.
Serbia surprises with a rate hike to 6%, its first in over three years
The National Bank of Serbia raised its key rate by 0.25 points to 6% to stop costly energy from spreading to other prices. Economists polled by Bloomberg had expected a hold.
Morning brief by email
The night's key moves and what matters today, in 2 minutes. One-click unsubscribe.
3M
7M
40M
60M
80M
250M